Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, August 30, 2013

Concrete Ramps Installed for Mid-Block Crossing

This past week, the sidewalk ramps for the mid-block crossing at Harrison Street were installed. The contractor also performed some general site clean-up and miscellaneous repairs to new and existing manholes.

The contractor is committed to watering the sod and ensuring the sod survives and remains healthy.  

The entire project is completed at this point with the exception of performing a few minor repairs and the pavement markings associated with the mid-block crossing at Harrison Street.

We thank you again for your patience and understanding during the construction process.

Monday, August 26, 2013

Work Mostly Completed

This past week, no work was completed on-site.

The contractor is committed to watering the sod and ensuring the sod survives throughout the year and a healthy lawn is restored.  

The entire project is completed at this point with the exception of performing a few minor repairs and the installation of a mid-block cross walk at Harrison Street.

We thank you again for your patience and understanding during the construction process.

Monday, August 19, 2013

Landscape Restoration Completed

This past week, the contractor completed installing and grading topsoil, installation of sod, pavement markings, removal of the southbound detour, and other miscellaneous tasks.

The contractor is committed to watering the sod and ensuring the sod survives throughout the year and a healthy lawn is restored.  

The entire project is completed at this point with the exception of performing a few minor repairs that were found during a final walk-through of the project.

We thank you again for your patience and understanding during the construction process.

Monday, August 12, 2013

Landscape Restoration On-Going

This past week, the contractor completed installing the asphalt surface layer along the entire roadway. The landscaping contractor was also on-site installing and grading topsoil in preparation for installation of sod.

Next week, the contractor will complete installing and grading the topsoil prior to sod installation. The contractor will also begin installing the sod within the parkways. The contractor has decided to install the sod now instead of waiting until the fall when the growing conditions are more favorable. The contractor is committed to watering the sod and ensuring the sod survives throughout the year and a healthy lawn is restored.  

Pavement markings will be completed once the topsoil installation is completed.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect until the landscapers are completed and the pavement markings are installed, hopefully by the middle to end of next week.

We thank you again for your patience and understanding throughout the entire construction process. As the topsoil and sod installation progresses, the lawns will look much nicer. Thank you for your understanding and tolerating a dug-up yard during the construction season.

Friday, August 2, 2013

Asphalt Surface to be Completed

This past week, the contractor completed installing asphalt driveways, storm sewer improvements, performed manhole adjustments within the roadway and parkway, landscape grading behind the curb, and milling the existing pavement near Central Road.

The contractor will install the asphaltic surface layer on Saturday, August 3rd starting at 7:00 AM.

Next week, the contractor will continue with the landscape grading and installing topsoil prior to sod installation. Sod installation will not be performed until the fall when growing conditions are more favorable.

Pavement markings will be completed once the topsoil installation is completed.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.

We thank you again for your patience and understanding throughout the entire construction process.