Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, July 26, 2013

Asphalt Binder Being Installed

This past week, the contractor completed the concrete curb & gutter, concrete sidewalk, and concrete driveway installation. The contractor also performed the fine grading of the aggregate base course. The 1st layer of asphalt binder was installed on Friday.  The 2nd layer of asphalt binder layer is scheduled to be installed on Saturday, July 27th. The contractor also performed some additional storm sewer improvements behind the concrete curb & gutter.  

Next week, the contractor will complete the storm sewer improvements, adjust the existing manholes, and perform landscape grading behind the concrete curb & gutter, around sidewalks, and storm sewers. The asphalt paving contractor will install the asphalt driveways.

It is anticipated the landscape contractor will begin grading and installing topsoil prior to sod installation. Sod installation will not be performed until the fall when growing conditions are more favorable.

Once all the landscape grading and topsoil installation is completed, the final lift of asphalt surface will be installed and the pavement markings will be completed.

The contractor is anticipating to work on Saturday, July 27th starting at 7:00 AM. The contractor will be installing the 2nd lift of asphalt binder.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.

Thank you in advance for your patience utilizing the posted detour routes and during the construction operations.

With the concrete curb & gutter and asphalt pavement installed, the project is starting to come to a close. The dust and bumpy roadway conditions are now behind us. We thank you again for your patience and understanding throughout the entire construction process.

Friday, July 19, 2013

Concrete Curb & Gutter Installed

This past week, the contractor completed the roadway excavation, installation of aggregate base course, and removal of sidewalks and driveways. The contractor also installed concrete curb & gutter on both sides of the roadway and concrete sidewalks along the project site.

Next week, the contractor will complete installing the concrete curb & gutter, sidewalks, and driveways and complete any remaining underground utility improvements. The contractor will also perform grading from the new concrete curb & gutter to the existing landscape and fine grading of the aggregate base course.

The contractor is anticipating to work on Saturday, July 20th starting at 7:00 AM. The contractor will be pouring concrete and performing grading work.

Asphalt paving is scheduled to start the week of July 29th.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.

Thank you in advance for your patience utilizing the posted detour routes and during the construction operations.

Saturday, July 13, 2013

Roadway Reconstruction On-Going

This past week, the contractor completed the storm sewer and water main improvements along the project site. All underground utilities are now nearly completed with only a few items remaining throughout the project. The contractor also began the roadway reconstruction process from Norwood Terrace to Central Road. The contractor first removed the existing asphalt pavement, then began excavating and installing a new aggregate base.

Next week, the contractor will continue to perform the roadway excavation process to Central Road. The contractor is also anticipating to install the concrete curb & gutter mid-week and concrete sidewalk at the beginning of the week. Prior to installing the concrete curb & gutter, residents will be notified regarding access to their driveways during the construction and curing process.

The contractor is anticipating to work on Saturday, July 13th starting at 7:00 AM.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.

Thank you in advance for your patience utilizing the posted detour routes and during the construction operations.

Monday, July 8, 2013

Underground Utilities Nearing Completion. Road Reconstruction to Start

Last week the contractor completed the connection between the existing water main and new water main at Karen Lane. The contractor also performed storm sewer installation along the north side of the project site.  

This week, the contractor will likely complete the storm sewer and underground utility improvements along the project site.  Once the underground utility improvements are completed, the contractor will begin the roadway reconstruction process, which will likely start later in the week or the week of July 15th.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.