Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, September 6, 2013

Only Minor Repairs Remain

This past week, the pavement markings for the mid-block crossing were installed and the contractor performed some miscellaneous repairs to complete the project.

Next week Village staff will perform a walk-through of the project to determine any deficient items that need to be addressed by the contractor prior to project close-out.

The landscape contractor will continue to water the sod they are confident the sod will survive and remains healthy.

We thank you again for your patience and understanding during the construction process.