Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Monday, August 26, 2013

Work Mostly Completed

This past week, no work was completed on-site.

The contractor is committed to watering the sod and ensuring the sod survives throughout the year and a healthy lawn is restored.  

The entire project is completed at this point with the exception of performing a few minor repairs and the installation of a mid-block cross walk at Harrison Street.

We thank you again for your patience and understanding during the construction process.