Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Monday, August 19, 2013

Landscape Restoration Completed

This past week, the contractor completed installing and grading topsoil, installation of sod, pavement markings, removal of the southbound detour, and other miscellaneous tasks.

The contractor is committed to watering the sod and ensuring the sod survives throughout the year and a healthy lawn is restored.  

The entire project is completed at this point with the exception of performing a few minor repairs that were found during a final walk-through of the project.

We thank you again for your patience and understanding during the construction process.