Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, August 30, 2013

Concrete Ramps Installed for Mid-Block Crossing

This past week, the sidewalk ramps for the mid-block crossing at Harrison Street were installed. The contractor also performed some general site clean-up and miscellaneous repairs to new and existing manholes.

The contractor is committed to watering the sod and ensuring the sod survives and remains healthy.  

The entire project is completed at this point with the exception of performing a few minor repairs and the pavement markings associated with the mid-block crossing at Harrison Street.

We thank you again for your patience and understanding during the construction process.