Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, August 2, 2013

Asphalt Surface to be Completed

This past week, the contractor completed installing asphalt driveways, storm sewer improvements, performed manhole adjustments within the roadway and parkway, landscape grading behind the curb, and milling the existing pavement near Central Road.

The contractor will install the asphaltic surface layer on Saturday, August 3rd starting at 7:00 AM.

Next week, the contractor will continue with the landscape grading and installing topsoil prior to sod installation. Sod installation will not be performed until the fall when growing conditions are more favorable.

Pavement markings will be completed once the topsoil installation is completed.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.

We thank you again for your patience and understanding throughout the entire construction process.