Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Monday, July 8, 2013

Underground Utilities Nearing Completion. Road Reconstruction to Start

Last week the contractor completed the connection between the existing water main and new water main at Karen Lane. The contractor also performed storm sewer installation along the north side of the project site.  

This week, the contractor will likely complete the storm sewer and underground utility improvements along the project site.  Once the underground utility improvements are completed, the contractor will begin the roadway reconstruction process, which will likely start later in the week or the week of July 15th.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.

Thank you in advance for your patience utilizing the posted detour routes and during the construction operations.