Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, July 19, 2013

Concrete Curb & Gutter Installed

This past week, the contractor completed the roadway excavation, installation of aggregate base course, and removal of sidewalks and driveways. The contractor also installed concrete curb & gutter on both sides of the roadway and concrete sidewalks along the project site.

Next week, the contractor will complete installing the concrete curb & gutter, sidewalks, and driveways and complete any remaining underground utility improvements. The contractor will also perform grading from the new concrete curb & gutter to the existing landscape and fine grading of the aggregate base course.

The contractor is anticipating to work on Saturday, July 20th starting at 7:00 AM. The contractor will be pouring concrete and performing grading work.

Asphalt paving is scheduled to start the week of July 29th.

The southbound detour along Washington Road between Norwood Terrace and Central Road will be in effect for the project entirety, around August 15th.

Thank you in advance for your patience utilizing the posted detour routes and during the construction operations.