Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, June 14, 2013

South Bound Detour in Effect

Last week the contractor continued to install water main and storm sewer along the project site. 

As of Thursday, June 13th, all southbound traffic is being detoured around the project site, while northbound traffic is allowed travel between Norwood Terrace and Central Road. This detour route will be in effect for the project entirety, around August 15th.

Next week, the contractor will continue to install water main and storm sewer along the project site. The contractor will begin making connections between the newly installed water main and the existing water main, the water main will be need to be shut-off to perform this work. Effect residents will be notified 24-hours in advance of any water main shut down.

Thank you in advance for your patience utilizing the posted detour routes and during the water main shut-downs.