Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, May 17, 2013

Work Started

Last week the contractor performed some storm sewer and sanitary sewer replacements along Washington Road.

Next week, the contractor anticipates to perform removal of previously marked trees, continue with storm sewer and sanitary sewer replacements, and begin water main installation.

Thank you in advance for your patience during the construction operations.