Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Friday, May 31, 2013

Water Main Continues

Last week the contractor installed water main at various locations throughout the project and performed sanitary sewer and storm sewer improvements.

Next week, the contractor will continue to install water main along the project site. The contractor will also perform testing on the previously installed water main.

Thank you in advance for your patience during the construction operations.