Project scope consists of roadway paving, water main repairs, storm and sanitary sewers repairs, and parkway restoration. The project improvements include:

· All new asphalt pavement
· Curb and gutter construction
· Storm sewer repairs
· Water main repairs
· Sanitary sewer repairs
· Sidewalk extension
· Driveway apron repairs and replacement
. Parkway sod restoration

Project Timeline
May 2013 – Start of Construction
October 2013 – End of Construction

Monday, May 6, 2013

The contractor, Lenny Hoffman Excavating, is anticipating to begin sanitary sewer improvements along Johns Park.

The contractor anticipates to begin work along Washington Road the week of May 13th.